Action plan



Pre-production Action Plan

 

9th November 2020- 22nd March 2021

Action

Time needed

What needs to be done beforehand

1.Create concept for film/extract

A few days

 

2.Finalise concept i.e. ensure it makes sense, characters and plot are developed properly

1 day

1

3.Produce a rough copy of script

2 weeks

1,2

4.Make storyboards

1 week

3

5. Create shot list

1 week max

 

6. Consider budgeting e.g. if there’s enough to cover costs of equipment or transport

A few days

1 ,3,4

7. Check availability of personnel i.e. make-up artists

1 week max

 

8.Decide where would be appropriate to film

1 day

3,4

 9.Contact the owner of chosen location, requesting filming permission

Could take up to 2 weeks, depends on how fast owner responds

6

10. Create a location release form for landowner to sign, proves consent

A few days

7

11. Location recce

1 day

8

12. Research equipment needed, where to get it from, expenses

A few days

4

13. Consider costuming, make-up (sfx, general), how much it would cost, what it should look like

1 week

3,4

14. Book equipment and personnel

A few days

5,6,11

15. Consider casting

 

 

16. Create risk assessments and consent forms

2 weeks

 

17. Cast required actors

A few days

15


 I have completed this activity as a way to keep an organised pre-production schedule.  I've achieved this by using a table on a word document to allocate what will need to be done, how long it should take and whether or not something else needs to happen before it can be started (I've chosen to complete this on word as it was the easiest way for me to understand). This action plan will ensure that my project will remain controlled and collected and will unlikely cause any unnecessary issues.